Use these commands to select the right panel view.
If you select
Risk Register in the
, then the only commands available in this menu are
Risk Comparison and
Activities.
Field/Option | Description |
None
|
When you select this option, then the view you selected in the Left Panel menu displays in the entire Acumen window.
|
Gantt Chart
|
Click this command to view the project schedule in Gantt chart format.
|
Uncertainty Inputs
|
Click this command to view the breakdown of uncertainty inputs.
|
Risk Exposure
|
Click this command to view and evaluate risk exposure in a histogram.
|
Risk Exposure Comparison
|
Use the Risk Exposure view to add multiple risk exposure scenarios to the risk comparison then click this command to compare those results using a tornado chart.
|
Risk Drivers
|
Click this command to view cost and schedule risk drivers in a tornado chart.
|
Risk Driver Comparison
|
Use the Risk Drivers view to add the current result set to the risk driver comparison, then click this command to compare those result sets in a single chart.
|
Risk Sensitivity
|
Click this command to view relationship and joint confidence level (JCL) between activities and/or costs in a scatter chart.
|
Critical Schedule Drivers
|
Click this command to view critical paths and near-critical paths that become critical due to risk.
|
Risk Register
|
Click this command to create and maintain project risks and integrate them into cost/schedule model.
|
Activities
|
Click this command to view the project schedule and set duration uncertainties.
This command only displays when you select
Risk Register from the
menu.
|